Hepcat Tattoos
Site Visit:
1st Phase:
We began by installing electric distribution box into the premises. The suspended ceiling was then installed followed by a hanging feature, which was made on site.
2nd Phase:
Partition walls had been constructed and decoration was now in place – All joint were taped and filled and emulsion was to be applied. We also installed electrical floor boxes and various power points throughout premises. We came up with a unique lighting design comprising of CAT2’s and low voltage down lighters which look particularly effective in lower natural light conditions.
Completed Project:
 |
 |
 |
By now all decoration was complete. A light was applied screed was applied to level floor off and a black and white chequered vinyl was installed along with furniture.
Time scale – 2wks
Client was delighted with the outcome and has recommended Allan Interiors to their clients.