Panasonic Shop (Silverburn Shopping Mall, Glasgow)
Main Contractor: Allan Interiors
Responsible for project management. Allan Interiors involved from design stage to handover.
1st Phase
Installed hoarding at entrance to prevent public access. Hoarding taped and filled to give clean finish
Electrical, Ventilation, Sprinkler, Raised Access Flooring and Fire Alarms (1st Fix) works carried out.
2nd Phase
3rd Phase
Installed new suspended ceiling with new light fittings. Electrical, Ventilation, Sprinkler, Raised Access Flooring and Fire Alarms (2nd Fix) completed.
Complete
Panel walls installed along with new TVs & Washing machines.
Client: Very satisfied
Site Works Completion: Approx 6 Weeks